Hundreds of workers are speeding up construction of a field hospital in District 7 (HCMC) to soon hand over and put into use.
Construction progress from July 14 to July 24 for 13 field hospitals, at the field hospital project in District 7, dozens of dump trucks and sand trucks on Dao Tri Street to enter the construction site. DDC mobilized more than 100 workers, working in 3 shifts (24/24 hours) to ensure the project handover schedule to the city.
This phase will hand over to the city by the end of July more than 2380 beds. By noon on July 19, the work had poured concrete to construct 13 foundations. Installing roofs and steel buildings for 5 rows, finishing 3 more blocks tonight. All workers implement the option “3 on the spot”, workers eat and sleep at the project.
In the beginning of next week, 200 workers will be mobilized to ensure the construction of a series of items: trusses, EPS panels, aluminum and glass, MEP….