Hoa Phat Cast Iron-Steel Complex

overview

  • Hoa Phat Steel Factory Coal Warehouse project is in charge of Dai Dung in the design, processing, manufacturing, configuration and installation of the main frame and finished structure.
  • Construction of 2 Hoa Phat coal warehouses started construction in 11 months, exceeding the required schedule but still ensuring the criteria of durability and bearing according to the standards of heavy industrial warehouses by the project management team of engineers and workers of Dai Dung.
  • DDC is proud to be the unit that both installs and processes, and ensures that the investor's production transportation is not interrupted and completely.
  • This is one of the national key projects located in Dung Quat Industrial Park - Quang Ngai Central, contributing a part to the mining and production of mines in the coal supply chain of Hoa Phat Iron and Steel Complex.

the process of ddc group

Project classification

Heavy Industry – Energy

Address

Vietnam

Year

2020

Investors

Hoa Phat Group - Vietnam

Mass

40.000 tons

Status

Completed

Area

30.000m2

Safe hours

> 500 giờ

Length

3000m

High

70m